An rendering of the crane that will be assembled and set up on Monday. It will be used to move the steel structure for the patio canopy from the parking lot, and over the clubhouse, to the back patio next week.
Back Patio Project Update March 24, 2023
Dear Members,
Back Patio Project construction will swing into high gear next week with the installation of the steel structure for the patio canopy.
A huge crane will arrive on Monday, March 27 and work is scheduled to be completed by Friday, March 31, as long as the weather cooperates.
Safety will be paramount during this process and as a result, access to the East side of the clubhouse, including the Men’s Locker Room and the Solarium, will be limited.
From Tuesday to Thursday, between the hours of 7 am and 5 pm, all levels of the Men’s Locker Room and the Solarium will be closed. Only the club's Facilities Manager will have access to the Men's Locker Room during these times.
If you require access to your locker please ask at Reception. Staff will do their best to retrieve personal items as promptly as possible, coordinating timing with the contractors, when the crane is not in operation over the clubhouse.
There will also be fewer available spots for parking to start the week. This situation is expected to improve daily as more of the steel structure is put into place.
If you have any questions or comments, please forward them to Facilities Manager David Harris – dharris@hgcc.ca.
Sincerely,