CONSTRUCTION UPDATE : CAMBODIA

Welcome to New Nordic Cambodia! Here you can find our weekly conctruction update from Sunsine Hotel & Resort

This week we have done soil back filling for the ramp, excavation for retaining wall basement floor, excavation for fresh water tank basement floor, cleaning pit for elevator basement floor, form work installation for retaining wall, brick wall installation ground floor, Purlin installation roof floor, floor and wall tile installation several floors, external wall plastering and wall painting, closing ceiling gypsum board with 1st skim coat several floors and rafter installation roof floor.